Here’s what happened this past week, May 07 to 10.
In High St, paving works continued in the footpath areas running from Nana’s Tea to Height of Health.
In O’Connell Square outside Hidden Hearing and Eurostore, excavation
works have begun in preparation for the installation of new ducting
and services.
In O’Connell Street the installation of the new sewer has been completed.
Between Pamela Scott and the Chamber of Commerce new ducting and services along with a concrete protection slab has been installed in advance of paving.
Meanwhile, paving works have continued on the footpath areas in front of the Old
Ground Hotel.